Total Tickets (May)
18
May Sprint
In Release
3
Pending sign-off
Active Risks
6
2 High ยท 3 Medium
Open To-Dos
14
Across 4 teams
Kanban Board โ May Sprint Tickets
May 2026
Backlog
Req. Collection ยท BRD3
Requirement Collection
NVP-101
Multi-currency Wallet Top-up Flow Redesign
BRD
NVP-104
Merchant Settlement Batch Processing v2
Requirement Collection
NVP-108
Agent Banking Offline Transaction Support
Req. Analysis & Design
PRD ยท UIUX ยท ISA4
PRD
NVP-092
Biometric Authentication โ Face ID Integration
UIUX
NVP-095
Loyalty Points Dashboard โ Customer Portal
ISA
NVP-098
Cross-border Remittance Compliance Engine
PRD
NVP-102
QR Code Payment โ Offline Mode Fallback
Development & Test
Dev ยท Int. Test ยท UAT5
Dev
NVP-078
Real-time FX Rate Feed โ Kafka Integration
Integration Test
NVP-081
KYC Document Verification โ Third-party API
UAT
NVP-085
Merchant Onboarding Self-service Portal
Dev
NVP-088
Push Notification Service โ iOS & Android
Integration Test
NVP-090
Card Transaction Dispute Management Module
Release
Pen Test ยท Reg. Test ยท Release3
Penetration Test
NVP-061
Payment Gateway SSL/TLS Upgrade v1.3
Regression Test
NVP-066
Core Banking API Rate Limiting & Throttle
Release
NVP-071
App Store Release โ v4.2.1 Hotfix Bundle
Done5
Done
NVP-042
User Onboarding โ OTP SMS Flow Revamp
Done
NVP-048
Transaction History Export โ PDF/CSV
Done
NVP-053
Admin Dashboard โ Role-based Access Control
Done
NVP-057
Currency Conversion Widget โ Homepage
Done
NVP-059
Fraud Detection Alert โ Rule Engine v2
Ticket Timeline, Team & Issues
4 Key Tickets
NVP-081
KYC Document Verification โ Third-party API Integration
๐ด Blocked
Team
JW
Jenny W.
Product Designer
Platform
RK
Ryan K.
Feature Owner
Platform
AL
Amy L.
UAT QA Lead
Platform
MT
Marcus T.
Solution Architect
Partner
DP
Diana P.
Partner BA
Partner
Issues & Blockers
๐ด BLOCKED: Vendor sandbox API returning 503 errors for 72+ hrs โ integration test halted
๐ก Test data set does not cover all document types required for target markets
โ ๏ธ SLA breach risk (RISK-001) โ escalation pending with vendor account team
Next To-Do
โ Escalate API outage to vendor CTO โ deadline 12 Jun (Ryan K.)
โ Prepare alternative mock service for UAT environment (Marcus T. ยท 14 Jun)
โ Expand test data matrix to cover all 12 document types (Diana P. ยท 16 Jun)
โ Update project timeline with revised UAT start date (Jenny W.)
NVP-092
Biometric Authentication โ Face ID & Fingerprint Integration
๐ต In Progress
Team
SL
Simon L.
Feature Owner
Platform
JW
Jenny W.
Product Designer
Platform
MT
Marcus T.
Solution Architect
Partner
Issues & Blockers
๐ก PRD scope expanded by 6 sub-requirements post sign-off โ delivery timeline impacted (RISK-005)
๐ก iOS Face ID SDK version conflict with existing auth library โ needs resolution before dev start
โ ๏ธ Security review for biometric data storage not yet scheduled with InfoSec team
Next To-Do
โ Finalise revised PRD with 4 deferred items confirmed (Simon L. ยท 13 Jun)
โ Resolve iOS SDK version conflict โ raise with mobile platform team (Amy L. ยท 14 Jun)
โ Schedule InfoSec review for biometric data handling (Jenny W. ยท 15 Jun)
NVP-061
Payment Gateway SSL/TLS Upgrade to v1.3
๐ก In Review
Team
RK
Ryan K.
Feature Owner
Platform
SL
Simon L.
UAT QA Lead
Platform
DP
Diana P.
Partner PM
Partner
Issues & Blockers
๐ก Penetration test findings: 2 medium-severity vulnerabilities identified โ patches under review
๐ก Certificate rollout schedule conflicts with scheduled maintenance window on 18 Jun
โ ๏ธ Regression test scope may expand if patch introduces breaking changes to payment flows
Next To-Do
โ Resolve 2 pentest findings โ patch review complete by 14 Jun (Amy L.)
โ Confirm new maintenance window with Ops team (Ryan K. ยท 15 Jun)
โ Prepare regression test plan covering patched modules (Simon L. ยท 16 Jun)
โ Partner sign-off on updated release date (Diana P.)
NVP-085
Merchant Onboarding Self-service Portal
๐ต In Progress
Team
AL
Amy L.
Feature Owner
Platform
SL
Simon L.
Product Designer
Platform
MT
Marcus T.
Partner SA
Partner
DP
Diana P.
Partner BA
Partner
Issues & Blockers
๐ก UAT environment missing production-equivalent merchant data โ impacting test coverage
๐ก Partner BA feedback on document upload UX requires design revision before UAT sign-off
โ ๏ธ Dependency on CMS content migration not yet confirmed โ portal content may not be ready at launch
Next To-Do
โ Provision UAT environment with anonymised merchant data (Simon L. ยท 13 Jun)
โ UX revision for document upload flow โ deliver updated prototype (Jenny W. ยท 15 Jun)
โ Confirm CMS content migration timeline with content team (Amy L.)
โ Partner UAT kick-off meeting โ schedule with Diana P. (Amy L. ยท 14 Jun)